To date, fully implemented installation of metal structures, filled overlap between the first and second floors, the installation of sandwich panels (made of 80%). In addition, prepared the ground under the floor slab, poured the foundations for the equipment of loading and unloading docks.
"At the moment, preparing for the beginning of works on roofing. A contract with a contractor who will soon commence work, - says the Deputy General Director of SC "Agropromkomplektatsiya" construction Alexey Grachev. - Start the installation of onsite utilities, the contractor begins installation of the networks of water, sewer inside of the distribution center. After this will begin pouring the floor plate".
Also today, work is underway on the device of the drainage tray from the territory of the RTS. In General, the object is ready on 40%.