In addition to the six-storey mill with a total area of 4.7 thousand square meters, the new production will be additionally installed an automated packing line flour in paper bags and built the warehouse in 1 thousand sq. m.
The total capacity of the complex on processing of grain will be 400 tons per day.
"At present, the main construction work is over, is finished and installation of equipment", - stated in the message.
Summer Elevator intends to complete commissioning and early fall to bring the new complex on the production capacity of 240 tons of grain per day. Later will be started the second module with capacity of 160 tons of grain per day.
Today JSC "Tabunskogo Elevator" includes two mills, kropacek, a feed mill, a bakery, a pastry shop by themselves and Elevator capacities.
According to system "SPARK-Interfax", in 2016 (the latest data), the revenues of the Elevator amounted to 1.38 billion rubles, net profit exceeded 32 million.
Photo: lovetextures.com
Translated by service "Yandex.Translation"