In the Kursk region continues construction of a second feed mill and silo GC "Agropromkomplektatsiya".
On the Elevator part of the work done by 75%, feed the plant is ready for 60%.
Подписаться на новости

At the moment we are finishing work in administrative building and production building. Laid network of heating, water supply, Sewerage, ventilation, electricity.

"In the main production building is now pouring the slab, the installation of metal sandwich panels for container stock, installation of equipment, says Deputy General Director of GK "Agropromkomplektatsiya" construction Alexey Grachev. - Already established 20 containers Elevator, installed two dryers. A fully ready laboratory, checkpoint, truck weighing, car wash, pump station, mechanical repair workshop, warehouse, outdoor storage, feed-through and the building is administrative-household case. In ABK imported furniture. Complete transformer substation".

Completing installation of equipment in the boiler room, where soon will begin preparing for commissioning. Warehouse storage on-going internal work – set lighting, fire-fighting equipment.

On Elevator parts installed process and electrical equipment. Upon completion of installation start of commissioning. Basic designs are collected.

 

For reference:

 

The design production capacity of the second feed mill Group in the Kursk region – 216 thousand tons per year. The Elevator is designed for simultaneous storage of 150 thousand tons of grain. Elevator part it is planned to put into operation in July, the entire plant – in the fall of 2018.



Translated by service "Yandex.Translation"
Источники: Agro2b
Friday, 26 April 2024
Thursday, 25 April 2024
Friday, 19 April 2024
Thursday, 18 April 2024
Wednesday, 17 April 2024
Tuesday, 16 April 2024
Tuesday, 09 April 2024
Monday, 08 April 2024
Friday, 05 April 2024
Thursday, 04 April 2024
Wednesday, 03 April 2024
Monday, 01 April 2024
All news